Constellation's Three Mile Island Nuclear Restart Gets Boost With FERC Waiver
What they're not telling you: FERC Hands Constellation Energy a $760 Million Gift Wrapped in Emergency Powers The Federal Energy Regulatory Commission just handed Constellation Energy the regulatory equivalent of a blank check: permission to transfer 760 megawatts of capacity rights from a retiring coal plant to restart Three Mile Island, bypassing the grid safety reviews that were supposed to protect ratepayers from exactly this kind of financial engineering. Here's the transaction: Constellation was ordered by the Department of Energy in 2025 to keep two coal units running at its Eddystone plant near Philadelphia under an "emergency energy shortage" directive. Because those units are now officially designated as non-capacity resources under the DOE's emergency order, Constellation argued their Capacity Interconnection Rights—essentially the right to push power onto the grid—became "free to be transferred." On June 1, 2026, FERC approved the waiver, letting those 760 MW rights move to Crane (Three Mile Island Unit 1), which is supposed to restart in late 2027.
What the Documents Show
What FERC approved against the objections of PJM Interconnection's own market monitor is a mechanism that lets Constellation circumvent $4 billion in transmission infrastructure upgrades that PJM engineers determined were necessary to safely deliver all 835 megawatts from the restarted nuclear unit. Those upgrades—including 765-kV and 500-kV transmission projects—aren't scheduled to complete until December 2030 at the earliest, with delays likely. FERC's waiver means the company can deliver 760 MW immediately without waiting for the grid to actually be ready. The regulatory sequence matters here. The DOE ordered Eddystone kept open under emergency authority.
Follow the Money
That designation made the plant's capacity rights "available" to transfer. FERC then approved the transfer based on criteria that Constellation's waiver "solves a concrete problem." But who benefits from defining it that way? Constellation gets $1.6 billion in federal and state subsidies plus guaranteed markets to restart a reactor that requires years of additional grid infrastructure investment. PJM's market monitor—the independent entity whose job is to flag when market rules are being exploited—objected to the waiver. FERC approved it anyway. The transmission engineers who said upgrades were needed?
What Else We Know
Overruled by the capacity transfer loophole. What gets obscured in the regulatory language is simple: Constellation negotiated access to grid capacity that doesn't technically exist yet. The company will be able to deliver 760 MW of power before the grid infrastructure that handles that power is complete. That's a $4 billion bill PJM ratepayers and grid operators will absorb. The cost of stabilizing the grid when Crane starts dumping power it's not fully connected to deliver—higher system costs, constrained operations—spreads across millions of households. The emergency authority that allowed this was issued under energy shortage rationale.
Primary Sources
- Source: ZeroHedge
- Category: Money & Markets
- Cross-reference independently — don't take our word for it.
Disclosure: NewsAnarchist aggregates from public records, API feeds (Federal Register, CourtListener, MuckRock, Hacker News), and independent media. AI-assisted synthesis. Always verify primary sources linked above.